With two referenda before the
Plainfield Library’s voters on March 15, getting information out to residents
on the proposed plan is a priority for Library Trustees and staff. The Library
offers a variety of ways to ensure all have an opportunity to get answers to
any questions they may have about the proposed plan: drop in Q&A,
representatives at community events, email form for questions, special
newsletters and more.
The following response is based on an
email reported to be circulating among residents, as forwarded to a Library
official. The text in red is the unedited
email, as forwarded. The text in black is answers to questions, clarifications
and context.
Subject: FW: Library
20
year/39M Bond for project ref
The building bond question on the ballot authorizes
a 20 year bond for $39,000,000 to build a new library, including buying
property, tearing down the old building, making a new parking lot, buying
furnishings and equipping the new building, including servers and computers.
100%
funded by levy increase ref
The building bond portion of the increase is 100%
funded by property taxes and will be paid off in 20 years, then automatically
removed from your tax bill. The bond repayment tax rate generally decreases
over time as new property is annexed or develops, spreading the fixed payment
amount over a larger tax base. The bond rate on the existing Library was 0.1657
in its first year, but dropped to 0.0094 by the final (20th) year. Local
funding match is required for the Live and Learn Construction Grant for which
the Library would apply: http://www.cyberdriveillinois.com/departments/library/grants/livelearn_construction.html
The limiting rate question is for an increase of
19% (0.0039 mils) to operate the proposed library, which is 3 times larger than
the current building. Property taxes comprise approximately 85% of the
Library’s annual operating revenue. The limiting tax rate increase is ongoing
for the operation of the Library, subject to the tax cap after the first year.
Building
Going from 27,160 SQ Feet to 72,000 SQ feet
Parking
lot to 170 spots
The estimated size and number of parking spaces
listed are correct. The design will be finalized following a successful
referendum. An updated Space Needs Analysis in 2015 initially called for 94,000
sq ft, but was reduced by the Library Board of Trustees to contain costs.
1989
ref failed, failed 1993, failed in 2009 for a 100,000 SQ ft facility reduced
from 130,000 ft
The three referenda listed were for different
purposes. The building bond referendum in 1989 failed. A revised building bond
referendum passed in 1990 with the support of the community for the library
and its services, resulting in the construction of the current Library. The
1993 limiting tax rate referendum, to operate the new Library that was 10 times
larger than the old, failed. Following that failure, half of the staff were
laid off, the materials budget frozen and hours of operation slashed to 48 per
week (68 per week today). Restoration of services occurred as the building boom
began in the late 1990’s. The 2009 limiting tax rate referendum was to fund
both building bonds and operation for a renovated and expanded main library and
a new branch. The original Space Needs Analysis showed a need for 130,000 sq ft
of Library space. The Library Board of Trustees proposed a plan for 100,000 sq
ft total library space. Not listed is the 1988 referendum to merge the
McClester-Nimmons Village of Plainfield Free Public Library and Plainfield Township
Library into the Plainfield Public Library District and expand its service
boundaries, which passed.
Marketing
Scheme-
1)Hired
a firm and haven’t disclosed amount paid to market Ref/design architecture
No firm has been hired to market the referendum.
The contract for Nagle Hartray Architects for pre-referendum services through
schematic design only was approved on April 15, 2015 for $99,000.00. Graham
Harwood from CCS International was contracted in January 2015 as owners’
representative with pre-referendum cost estimating for $42,400.00. The
Plainfield Library’s monthly financial reports are included in the Board
packets posted on the Citizens Information Center web page: http://plainfieldpubliclibrary.org/about/citizens-information-center.aspx
Also included in the packets is supporting documentation for Action Items on the
agenda, including contracts.
2)
Message is that average property tax will only go up $200.00 per year- that is
from a sample in the lower end homes in the Bolingbrook Portion of the
district- Homes in Plainfield Township that fall in the Lib District est.
$350-400 per year, est. Wheatland $400-650 per year.
American Fact Finder, which is the latest census
information, was the source for median home values in 2014 (most recent year available).
Those were:
Village of Plainfield - $289,300
Plainfield Township - $193,500
Wheatland Township - $358,400
The estimated increase for the median home value in the Village of
Plainfield is $172.19, for Plainfield Township is $111.38 and for Wheatland
Township is $216.04. Homeowners determine their own home’s estimated increase using
the cost calculator found here: http://plainfieldpubliclibrary.org/about/fmv-calculator.aspx
3) FUD-
Fear of Uncertainty and doubt- if it doesn’t pass, capital improvements that
have been ignored/not budgeted for
What happens if the referenda fail is based not on fear,
uncertainty or doubt, but fact. Capital needs have been at the forefront of the
Library’s budget and planning process. The Building Evaluation 2-2012 outlines
the base capital needs for keeping the current facility operational in the long
term. That report, along with Strategic Plan 2011 to 2015, Strategic Plan 2016
and Beyond, and Long Range Budget Plan FY14-FY17 can all be found in the Other
Documents section of the Board of Trustees web page here: http://plainfieldpubliclibrary.org/about/board.aspx
Necessity:
Page
72/76 has a staff shower room in the schematics
The Schematic Building Program shows a staff shower
room with an allotment of 75 sq ft, which was intended to also serve for performers
in the large event space, combining meeting rooms to seat 290. With the
Schematic Building Program listing 77,000 sq ft of space, the final design
process, following successful referenda, will include trade-offs or combining
spaces, such as adding a shower stall to an accessible restroom. Green design,
if the Library Board decides to pursue LEED certification, includes features
like a shower room for staff to support bicycling to work.
Drive
through book drop causing traffic/safety management- much more parking lot
space required
A drive up book return and service window eliminate
the hazard of cars blocking traffic flow in front of the building in order to
return materials, as seen with the current building, and provides safe,
convenient access. Delivery
and receiving are also accessed by the service
drive in the rear. Maintaining an adequate amount of parking was the #1 public comment
received about the downtown site. Again, the design will be finalized following
successful referenda.
Exponential
expansion of space for programs that will compete with the private sector- some
of which are already offered by the YMCA
Program attendance has grown exponentially – 2,191%
since 1993, the first year program attendance was tracked. Classes and programs
are a huge part of 21st century public library service. These services reflect
the changing world we live in, utilizing the latest technology and responding
to the evolving needs of our community. The YMCA and private sector businesses
may offer some similar programs, but their missions are different. A public
library by definition provides access to knowledge, information and works of
the imagination and gives that access freely to all. The Library partners with
public and private organizations to further the reach of each by pooling
resources when it makes sense to do so.
No
scientific Poll showing the residents support this proposal when given the true
scope of the project. – they were given a push poll
Public Research Group, from Naperville, worked with
the Library Board of Trustees and staff, first to determine what information
they were seeking and then how to get that information from respondents. The
benefit of using a professional survey company is their expertise in developing
questions that are unbiased and follow up to confirm the answers given. The
report on that telephone survey can be viewed here: http://plainfieldpubliclibrary.org/about/pdf/2015-09-Telephone-Survey-Final-Report.pdf
No
strategic planning/capital replacement plan- ED since 2000, ADA/Building code
violations need attention
As item 3) above shows, the Library Board of
Trustees has worked diligently to maintain a building with myriad structural
and design issues. Compliance with full current building code is triggered when
a significant investment is made in the existing building. Addressing the work
identified in the Building Program 2-2012 would trigger this compliance. http://www.plainfieldpubliclibrary.org/general/board/Building%20Evaluation%202-2012.pdf
P 76 to see the shower
room planned for the library
- Links to the Library’s web page.
If you have further questions, stop
by a drop in question and answer session, ask a Library representative at a
community event, submit questions online via the web form, call, text or chat
with a librarian. Dates and times of drop in sessions and Library
representatives at community events are available here: http://plainfieldpubliclibrary.org/about/pdf/timeline-012016.pdf